Electric Rate Schedules

Schedule CT
General Service - Demand Metered

Applicability

This schedule is applicable to 115 kV service to the Northern California Power Agency (NCPA) Combustion Turbine Installation pursuant to agreement between Alameda Power & Telecom (Alameda P&T) and NCPA.

Rates

Monthly Charges
  Distribution Public Purpose Generation Total
per kWh $0.02687 $0.00300 $0.04464 $0.07451
per kW Metered Demand $1.50 - $1.75 $3.25
per meter $225.00 - - $225.00

State and Local Taxes

To the above charges will be added any applicable state and local taxes (refer to Rider ERS for current tax rate) and charges for the state solar PV program (refer to Rider PV).

Definitions and Special Conditions

  1. METERED DEMAND
    The Metered Demand in any month is the maximum average power taken per meter during any 15-minute interval in the month, provided that, in case the load is intermittent or subject to violent fluctuations, Alameda P&T may use a 5-minute instead of a 15-minute interval.
  2. DISTRIBUTION CHARGE
    The charge for delivery of electric power at the local level, including billing and metering costs.
  3. PUBLIC PURPOSE CHARGE
    The California state-mandated charge supporting funding of energy efficiency, new renewable resources, low-income, and research and development programs.
  4. GENERATION CHARGE
    Charge recovering the cost of providing energy supply including generation and transmission costs.
  5. PRIMARY VOLTAGE DISCOUNT
    A voltage discount of 4.5% will be applied to all charges except taxes provided delivery continues to be made from Alameda P&T's 115 kV distribution line.
  6. POWER FACTOR
    Charges for any month as computed above will be adjusted for the power factor according to Rider PF.
  7. RULES and REGULATIONS:
    Other conditions, as specified in Alameda P&T's Rules and Regulations, shall apply to this rate schedule.

ADOPTED:  June 16, 2008
RESOLUTION NO. 4784
(Superseding Rate Schedule CT Effective August 1, 2003)

Effective: July 1, 2008