Schedule D-2
Multi-Family Residential Service
Applicability
This schedule is applicable to service for domestic power service supplied to
multi-family accommodations through one master meter on a single premise. This
schedule is closed to new installations.
Rates
| Monthly Charges |
| |
Distribution |
Public Purpose |
Generation |
Total |
Tier I:
Baseline Quantities, per kWh |
$0.04955 |
$0.00300 |
$0.05032 |
$0.10287 |
Tier II:
101-130% of Baseline, per kWh |
$0.05335 |
$0.00300 |
$0.06055 |
$0.11690 |
Tier III:
Over 130% of Baseline, per kWh |
$0.08452 |
$0.00300 |
$0.09541 |
$0.18293 |
State and Local Taxes
To the above charges will be added any applicable state and local taxes (refer to Rider UUT and Rider ERS for current tax rates) and charges for the state solar PV program (refer to Rider PV).
Definitions and Special Conditions
- RESIDENTIAL DWELLING UNITS
It is the responsibility of the customer to advise Alameda P&T within 15 days following
any change in the number of dwelling units wired for service.
- MISCELLANEOUS LOADS
Miscellaneous electrical loads such as general lighting, laundry rooms, general maintenance,
and other similar usage incidental to the operation of the premises as a multi-family
accommodation will be considered as domestic usage, billed under this tariff, where there is
only one meter on the premises.
- BASELINE RATES
Baseline rates are applicable only to residential usage billed under a residential rate
schedule.
- DISTRIBUTION CHARGE
The charge for low voltage delivery of electric power at the local level, including billing
and metering costs.
- PUBLIC PURPOSE CHARGE
The California state-mandated charge supporting funding of energy efficiency, new renewable
resources, low income and research and development programs.
- GENERATION CHARGE
Charge recovering the cost of providing energy supply including generation and transmission
costs.
- TIER I (BASELINE) & TIER II (101-130% of BASELINE)
QUANTITIES
Baseline quantities vary for summer and winter season and depending on the primary
heat source (gas or electric). The following quantities of electricity are to
be billed at the Tier I and Tier II rates:
| PRIMARY HEAT SOURCE |
SEASON |
BILLING CODE |
Tier I kWh Per Dwelling Unit PER MONTH |
Tier II kWh Per Dwelling Unit PER MONTH |
| NATURAL GAS/OTHER |
Summer |
B |
158 |
159-206
|
| NATURAL GAS/OTHER |
Winter |
B |
186 |
187-241 |
| PERMANENTLY INSTALLED ELECTRIC HEAT |
Summer |
H |
240 |
241-313 |
| PERMANENTLY INSTALLED ELECTRIC HEAT |
Winter |
H |
411 |
412-534 |
- TIER III (OVER 130% of BASELINE)
All usage in excess of Tier II will be billed at the Tier III rate.
- SEASONAL RATE CHANGES
Summer and winter Tier I and Tier II (Baseline) quantities will normally be billed
without seasonal proration for six consecutive billing periods starting with
the beginning of the May and November billing cycles, respectively.
- MINIMUM MONTHLY CHARGE
Monthly charges shall not be less than $5.00 per dwelling unit.
- RULES and REGULATIONS
Other conditions, as specified in Alameda P&T's Rules and Regulations,
shall apply to this electric rate schedule.
ADOPTED: July 16, 2008
RESOLUTION NO. 4784
(Superseding Rate Schedule D-2 Effective July 1, 2006)
|
Effective:
July 1, 2008 |
|