Schedule OL
Outdoor Street and Area Lighting
Applicability
This schedule is applicable to lighting provided to streets, private parking
lots, other publicly dedicated areas or paths readily accessible to Alameda Power
& Telecom (Alameda P&T) personnel. This schedule is not applicable to
lighting service rendered to the City of Alameda for its street lighting system,
which is covered under Schedule MU-2. The monthly usage
charge includes the energy provided for lighting, as well as the cost and
replacement of lamps, globes, and sensors. If the customer desires coverage for
replacement and maintenance of light fixtures and/or light poles, Alameda P&T
will contract to provide such coverage at the optional rates shown below.
Rates
Unmetered Usage
| Monthly Charges |
| Service charge per customer |
$23.00 |
|
Usage charge per lamp or fixture |
| |
High Pressure Sodium Vapor Lamps |
| |
Lamp Watts |
kWh/month |
Usage Charge |
| |
35 |
15 |
$1.29 |
| |
50 |
22 |
$1.89 |
| |
70 |
31 |
$2.67 |
| |
100 |
44 |
$3.79 |
| |
150 |
65 |
$5.60 |
| |
200 |
87 |
$7.49 |
| |
250 |
102 |
$8.79 |
| |
400 |
163 |
$14.04 |
| |
Fluorescent Fixtures |
| |
Lamp Watts |
kWh/month |
Usage Charge |
| |
440 |
166 |
$14.30 |
Metered Usage
| Monthly Charges |
| |
Distribution |
Public Purpose |
Generation |
TOTAL |
| Per Meter |
$23.00 |
- |
- |
$23.00 |
| Per kWh |
$0.04129 |
$0.00300 |
$0.04184 |
$0.08613 |
Optional Fixture and Pole Coverage
| Monthly Charges |
TOTAL |
| Per Fixture |
$1.50 |
| Per Pole |
- Standard 30' fiberglass pole
|
$1.50 |
- Customized 14' decorative pole
|
$3.50 |
State and Local Taxes
To the above charges, both metered and unmetered, will be added any applicable state and
local taxes (refer to Rider UUT and Rider ERS
for current tax rates).
Definitions and Special Conditions:
- BURNING SCHEDULE
Service for unmetered usage will be calculated by Alameda P&T's Engineering Department
(approximately 4380 hours per year).
- DISTRIBUTION CHARGE
The charge for low voltage delivery of electric power at the local level, including billing
and metering costs.
- PUBLIC PURPOSE CHARGE
The California state-mandated charge supporting funding of energy efficiency, new renewable
resources, low-income, and research and development programs.
- GENERATION CHARGE
Charge recovering the cost of providing energy supply including generation and transmission
costs.
- SERVICE VOLTAGE
Service will be furnished at the nearest available voltage.
- SERVICE CONNECTION
Service shall be at points convenient to Alameda P&T's lines, and connection shall be
made at the customer's expense.
- NON-PROFITS
At the discretion of Alameda P&T's General Manager, nonprofit, public benefit
corporations, as defined by the Internal Revenue Code, may be granted an exemption from the
Service charge for the purpose of providing area lighting for security and safety.
Organizations should submit a written request to the General Manager. Requests will be
reviewed on a case-by-case basis.
- RULES and REGULATIONS
Other conditions, as specified in Alameda P&T's
Rules and Regulations,
shall apply to this electric rate schedule.
ADOPTED: July 21, 2003
RESOLUTION NO. 4585
(Superseding Rate Schedules L-1 & L-2 Effective July 1, 2001)
|
Effective: August 1, 2003 |
|